Enhancing Preparedness Through One ADB for Transport Projects in South Asia · 57190-001

Drain the slope.
Water the village.

A US$1.99 million JFPR grant on the ADB-financed Assam SASEC Corridor (L4265), Route A-23 Package III, Thanalambra to Lower Haflong. Horizontal drainage borings steady an active landslide cluster at Ch 77+300. The groundwater they release is stored and piped to Choto Wapu, a farming village with no reliable water source.

Landslide sites assessed along the 30.06 km profile below · Site 11, JFPR target
01

The corridor, stitched from the drawings

Alignment, carriageway, right of way, breast walls and earthwork limits come from the plan drawings (UTM 46N), placed on satellite imagery. The long section beneath holds 2,987 levels at 10 m centres from the profile drawing. Move along either one and the other follows.

Ch —
Design road level—
Existing ground—
Cut / fill—
Design grade—
Breast wall—
Nearest structure—

Hover the long section or the road line. Drag on the strip below the section to zoom in.

02

Twelve landslide sites, one chosen for the grant

The field mission of 31 March – 2 April 2026 inspected all 12 sites marked for mitigation on Package III. Each card shows what the site needs, what the road project already plans, and whether its groundwater can reach Site 11. Open a card for the report's plan, cross-section and photographs, and for the DXF ground section where one exists.

03

Why Site 11, Ch 77+300

The road design moves the new alignment uphill and plans no treatment at this site. The specialist's assessment is that the slide blocks are spreading uphill and sideways, so the new road would be at risk again. Drainage boring treats the cause, and the water it releases is what the village is short of.

Ground section from SITE-11.dxf Profile X-X
Design overview, Site 11 and surroundings Report fig. 3.2.13 – 3.2.17
04

How horizontal drainage boring stops a slide

A landslide in clay moves when water pressure builds up on the slip surface. Borings drilled slightly uphill from the toe pierce the slip surface, vent that pressure and let gravity carry the water out. In Japan this is a basic landslide countermeasure, but it has rarely been used in India. Site 11 would be the pilot.

0

The sketch is a schematic, not an analysis: it shows the mechanism the report describes, with the water table falling as more borings reach the aquifer.

Already proven on this road emergency borings, June 2023
05

From landslide to village tap

Annual rainfall is high, but it falls in four to five months. Choto Wapu carries water from about 10 km away in the dry season, and its 0.4 ha pond lies below the houses, so it cannot feed them by gravity. The proposal stores drained and rain water in three reservoirs set one above another in the valley west of the village, then sends it down by gravity.

Water balance, Site 11 catchment report method, live
Peak flood the spillway must pass
Reservoir sizing
06

Cost estimate, ₹14.41 crore · US$1.55 million

Prepared with PWRD and its consultants using the loan project's item codes and rates (Table 3.2.4). Slope protection is US$562,140 and water supply US$987,537. Group the estimate by component, location or package, and switch currency.

Select a block or a row to see its specification.

07

Fifteen months, investigation to monitoring

The report's implementation programme (Table 6.1) runs from investigation through detailed design and construction to operation and maintenance. In O&M, villagers clean the channels and maintain the filter, so community awareness runs almost from the start.

08

Before the monsoon, three places that cannot wait

The mission found three spots on the live construction front that need action before the rains, separate from the grant works.

09

The road design in numbers

These figures are read directly from the DXF drawings: the horizontal curve tables, the profile levels and gradients, the cross-drainage schedule and the breast wall lines.

Horizontal curve radii 137 HIPs
Design speed on curves
Cross-drainage structures
Depth of cut and fill along the road
10

Sources and method

Report

Final Report, “Enhancing Preparedness Through One ADB for Transport Projects in South Asia – Slope Protection Specialist (57190-001), TA-10245 REG”, prepared by Takayuki Mayumi for the Asian Development Bank, 30 May 2026, 58 pages. All site descriptions, costs, quantities, design parameters and the programme come from it. Figures are reproduced with their original captions.

Drawings

HAFLONG Plan R1 and Profile A23_3 (dated 30-08-25), and SITE-10, SITE-11 and SITE-12 sheets (DXF). Alignment, carriageway, right of way, curve tables, culvert schedule, breast walls and earthwork limits were read from the plan. Design and ground levels at 10 m centres and gradients came from the profile. Ground sections, borehole positions, slip surfaces and groundwater lines came from the site sheets. Coordinates were converted from UTM zone 46N to WGS84.

Notes

Breast wall coverage counts 10 m stations with a breast wall line within 14 m of the centreline. Cut and fill is design level minus ground level at the centreline. Borehole depths to the slip surface and groundwater were measured off the DXF section geometry. Satellite imagery: Esri World Imagery; terrain: OpenTopoMap; streets: OpenStreetMap contributors.

Figures were read from the report and drawings by PlusBrains. PB can make mistakes — please double-check against the signed documents.